Glenview Construction Updates
This page contains updates and information for families, staff and the Glenview PS community.
December 2024 Construction Updates
Dec. 17, 2024
Hello Glenview PS families,
As we prepare to embark on the winter break, we would like to take this opportunity to update you on the progress of our school gym construction.
We are happy to report that we have made a lot of progress and we are working hard to have construction completed in late February.
Gym Slab on Grade:
Preparation work for the gym slab on grade is complete.
Concrete pouring is expected to be finished this week.
Blueskin Work:
Installation of Blueskin for the low and high roof parapets has started and is progressing with some adjustments due to weather conditions.
Parking Lot Preparation:
Wood supports have been installed to set up temporary light fixtures in the parking lot.
Plan for Dec. 16 - 27:
Cut concrete joints for the gym slab on grade.
Complete the high and low roof metal deck.
Finish all Blueskin installations.
Complete wood framing for the low roof parapet in preparation for waterproofing.
Attend a startup meeting with GRRC Roofing for roof work (scheduled for Thursday, Dec. 26).
Additional Coordination:
Awaiting a WindSpec update on aluminum window fabrication progress and installation dates.
Working with the sub-contractor to begin partition block wall installations for the new washrooms and change rooms.
Weather Challenges:
Progress continues but was impacted during the week of Dec. 9 - 13 due to snow, rain and low temperatures.
Concrete pouring was postponed twice due to rain.
Blueskin work was delayed as wet and windy conditions impacted wall preparation.
We again thank you for your continued support and patience as we work to create a fantastic and welcoming space for everyone.
Sincerely,
Nick Frankovich
Superintendent of Education
November 2024 Construction Updates
October 2024 Construction Updates
October 29, 2024 - Information for Glenview PS Families
We’re excited to share updated photos on the progress of our school gym construction. Here is what you can expect to see over the next few weeks:
Masonry Block: Completion is expected by the end of this month.
Steel Joists: Scheduled to arrive next week, which will help us move forward with the next phase.
Roof Construction: Work is set to begin in mid-November.
Thank you for your continued support and patience as we work to create a fantastic space for our Glenview students, staff, and school community!
Sincerely,
Nick Frankovich
August 2024 Construction Updates
Aug. 30, 2024 - Information for Glenview PS Families
Aug. 30, 2024
Dear Glenview Public School community,
We hope you have been enjoying your summer and are as excited as we are for the start of a new school year. As the construction of our new gymnasium continues, we would like to share the areas of our safety plan that will set students and staff up for a safe return to school.
The safety of our students and staff is our highest priority and we are working diligently to minimize any disruption to our daily school activities. To help ensure the safety of all students, families and staff, the following procedures will be in place:
Construction Site Boundaries and Access
Fencing: The construction area will be fenced off completely to prevent unauthorized access.
Site Access: Construction vehicle access will be through the main gate only and will be minimized and controlled.
Within the school, the construction site will be sectioned off with restricted access to construction personnel only.
Signage: Clear and visible signs are displayed around the site to indicate restricted areas and identify hazards.
Traffic Management
Parking: The parking lot will remain closed through September.
Arrangements have been made to secure 20 staff parking spots at St. Matthew's Anglican Church.
Parent/guardian parking will be limited to street parking where permitted.
Pedestrian Safety: Students, families and staff are being asked to exercise caution and be mindful of the extra activity around our school property, especially during drop-off and pick-up times.
Students who walk or bike to school, please visit the Walk and Wheel to School webpage on hdsb.ca for tips on how to get to school safely.
Staff and families are encouraged to review the transportation safety reminders outlined in Halton Regional Police Service’s Project Safe Start initiative.
As a reminder, photos of the construction progress continue to be added to the Glenview Construction Updates webpage.
Thank you for your support and understanding. We look forward to welcoming students to school on Wednesday, Sept. 4.
Sincerely,
Nick Frankovich
Superintendent of Education
Reg Farnand
Principal
Ian Gaudet
Superintendent of Facility Services
Aug. 23, 2024 - Glenview Gymnasium and Site Work Update
As we approach the 2024/2025 school year, construction on our new gymnasium continues. A safety plan has been developed and will be shared with staff for review and feedback before being finalized and shared with parents/guardians.
The parking lot will remain closed through September. Alternative arrangements are being made for staff parking. Parent/guardian parking will be limited to street parking where permitted. Physical education classes will continue at Active Aldershot and St. Matthew's Anglican Church until construction is complete.
Thank you for your support and understanding. We look forward to welcoming students to school on Wednesday, Sept. 4.
Below you will find the worksite progress as of August 29, 2024.
Glenview Gymnasium and Site Work Photo Progress
June 2024 Construction Updates
June 28, 2024 - Glenview PS Gymnasium Update
Dear Glenview Public School community,
I hope you and your families enjoyed a fun last day of school today.
With the approval of the Ministry of Education and the continuing advocacy and support of MPP Natalie Pierre, we continue to make progress toward the new gym construction. I’m happy to share with you that construction on the new gym will begin on Tuesday, July 2.
The safety of our students and staff is our highest priority. A safety plan has been developed to ensure the safety of the school community throughout construction, both in the summer months and when students and staff return in September.
During the summer months, the entire west side of the school will be fenced off. This includes the parking lot, previous garden area and beyond the playground swings.
We will provide construction updates through the Glenview Construction Updates webpage during the summer to keep you informed on the progress. We remain optimistic that we will be able to open the gym in January 2025.
Prior to school starting in September, we will provide additional information about procedures in place to ensure the safety of students and staff once they return to the building.
Thank you for your continued support and patience.
Have a wonderful long weekend and a safe and relaxing summer.
Sincerely,
Nick Frankovich
Superintendent of Education
June 20, 2024 - Glenview PS Gymnasium Update
June 20, 2024
Dear Glenview Public School community,
I am writing to provide an update on our new gym. As you know, the Government of Ontario provided approval for the Halton District School Board (HDSB) to construct a double gymnasium at Glenview PS. The tender process, which closed on May 31, revealed that the cost associated with this project exceeds the Ministry-approved budget.
Requests to spend more than the approved budget can be made through a Minister’s exemption. HDSB Business Services, Facility Services and Planning teams are currently working with Natalie Pierre, MPP of Burlington, staff at the Ministry of Education, and the new Minister of Education, Todd Smith, to expedite the approval process.
HDSB Facility Services staff and the design team are working with City of Burlington staff to finalize the Site Plan Approval and Building Permit comments so both can be issued as soon as possible.
We have also scheduled a meeting in the coming days with the successful contractor to ensure the project remains on track for when approvals are secured. It is our hope that this additional step will not impact our goal of opening the gym in January 2025.
Thank you for your continued support and understanding as we work through this process.
Sincerely,
Nick Frankovich
Superintendent of Education
June 13, 2024 - Glenview PS Gymnasium Update
Dear Glenview Public School community,
I am writing to provide an update on the construction of the double gymnasium at Glenview PS.
The tender for this project closed on May 31. This process has identified that the costs associated with building the new gymnasium are higher than what was previously approved by the Ministry of Education.
Requests to spend a greater amount of the Halton District School Board’s Proceeds of Disposition than originally approved requires additional approval from the Ministry of Education. While we do not expect this to be a lengthy delay, construction will not begin on June 17 as originally planned.
It is our hope that this additional step will not impact our goal of opening the gym in January 2025. We will provide further updates with additional information as it becomes available.
Thank you for your continued support and understanding as we work through this process.
Sincerely,
Nick Frankovich
Superintendent of Education
April 2024 Construction Updates
Apr. 26, 2024 - Glenview PS Gymnasium Update
Dear Glenview Public School community,
I am very pleased to share the news that the Government of Ontario has provided approval for the Halton District School Board to construct a double gymnasium at Glenview PS. We have also received approval to move ahead with tendering the project so that construction can begin as soon as possible.
We anticipate construction will begin in June. Our goal of opening the gym in January 2025 remains unchanged.
The safety and well-being of our students and staff will remain our highest priority throughout the construction process. I will provide another update with additional information once we are notified of the date construction will commence.
For further information, please view the Q&A and timeline of events available on our Glenview Construction Updates webpage.
Thank you for your continued patience and understanding as we work toward creating a new and improved space for our school community.
Sincerely,
Reg Farnand
Principal
February 2024 Construction Updates
Feb. 6, 2024 - Glenview PS Gymnasium Update
Dear Glenview Public School families,
I am writing to provide everyone with an update on our new gym. As you know, the gymnasium roof of Glenview PS collapsed last year and since then, we have been in the progress of constructing a new 6,450-ft2 double gym, which is nearly twice the size of our previous gym.
Having presented preliminary site plans to the City of Burlington in December, our anticipated Municipal and Ministry approval dates have shifted within our timeline. However, I am pleased to share that we are still fully anticipating the gym to open in January 2025.
Building a larger gym will ensure we are meeting both the current and future needs for the Glenview PS community. Although the process requires additional approvals and steps, the new facility will allow us to deliver enhanced physical education for years to come.
The safety and well-being of students and staff is our highest priority. In anticipation of the upcoming construction activities, we have completed the pathway connecting our school to St. Matthew's Anglican Church to allow for ease of access for students and staff. We have also relocated the community garden to ensure continued access for the community to benefit from the garden without disruption.
I appreciate your patience and understanding as we move through this process and I look forward to an improved facility that will reflect and meet the needs of our entire community.
Sincerely,
Reg Farnand
Principal
August 2023 Construction Updates
Aug. 29, 2023 - Information Session for Glenview PS Families
Dear Glenview Public School families,
Thank you to everyone who joined us this afternoon for the information session. For those who were unable to attend, we are writing to provide you with a summary of the session.
Background of School
Glenview PS was built in 1951 with an addition in 1952 and another in 1958. The school size is 3,147 square metres and sits on 2.31 hectares of land.
Specific to the gymnasium, a rooftop unit was added for ventilation measures in 1991.
The roof was replaced in 2017. The roofing was replaced with like-for-like insulation and built-up roofing material.
What Happened
Families can review the detailed timeline of events. Below are the details of the collapse, as summarized by the structural engineer.
The timber roof trusses that span the width of the gym, supporting the subject roof top unit, experienced significant stress.
Upon our review, it appeared that the roof unit (and HVAC unit) was placed on the roof some time after original construction (not part of the original build).
The structure, being timber, is subject to humidity changes and some of the larger timbers likely had drying shrinkage (cracks). This is not uncommon. Over time, the members reacted to the additional loading, resulting in the stresses noted.
To add to this, a heavy rainstorm the day before, compounded with the sagging roof, added water load due to ponding and ultimately caused the roof to collapse.
Glenview School Inspections
The HDSB reviews all schools regularly and through a variety of lenses and mechanisms that support our operations and maintenance planning.
Roof inspections are completed every six months by our team members and these were conducted at Glenview PS.
Asbestos containing material inspections were conducted in July of 2016. No asbestos containing materials were present in the gymnasium. The gym storage rooms contained non-friable asbestos containing floor tile and non-friable asbestos containing cement board on the walls. These were properly disposed of by our demolition contractor.
Through the Ontario Ministry of Education Assessment Program, an audit of Glenview PS was completed in September 2018. This assesses the needs of the school in terms of mechanical, electrical, site, architectural and structural needs.
At the time of this inspection, minor brick spalling, repointing of mortar and sealing of some joints was noted.
Glenview PS has undergone an inspection of all classrooms and other spaces to ensure the remainder of the school is structurally sound and safe for returning staff, students, and community.
Facility Services staff will review our inspection programs with third-party expertise to ensure that we meet or exceed industry standards.
Assessment of other HDSB Schools
The gym structure at Glenview PS is unique and while we continue to review our other schools, we believe that this unique wooden truss is the only one in the Halton District School Board.
Similar aged schools in the local area have been inspected and have steel trusses.
The HDSB has reviewed similar structures and spans (gyms and libraries) in our inventory over the summer months. None have been identified.
Interim Measures
The HDSB has reviewed numerous options for alternate physical education spaces for this school year. We are looking to proceed with physical education at St. Matthew On The Plains and Active Aldershot. Partnerships with these facilities would begin in October/November 2023 as students are able to have physical education outdoors in the warmer months.
Please note that Active Aldershot would require students to cross the street at the crosswalk on Plains Road. We are exploring various options, including having parent/guardian volunteers walk with classes to support student safety, as well as a shuttle which could transport students and staff to the facility. We are requesting feedback from parents/guardians on these options, as we understand parents may have concerns about this.
New Gym Plans
As the former gym does not meet today’s standards for size and amenities, we are proposing a new double gym that is 6450 sf, nearly double the size of the previous gym. You will find the approximate approvals and timelines below.
The safety of our students and staff is our highest priority. During construction, we will have a detailed safety plan to ensure the safety of students, staff and families.
Approvals and Timeline
Board approval – September 2023
Ministry approval – October 2023
Municipal approvals – site plan and building permit
Tender – December 2023
Award – January 2024
Construction – 12 months
Grand opening – Approximately January 2025
Sincerely,
Nick Frankovich
Superintendent of Education
Ian Gaudet
Superintendent of Facility Services
July 2023 Construction Updates
July 10, 2023 - Update on Glenview PS Gym Roof
Dear Glenview Public School families,
I am writing to update you on the Glenview PS gymnasium roof damage. I understand there are many questions regarding the circumstances and timelines of the gym roof collapse and the rebuilding of the gymnasium.
I want to begin by underscoring that the safety and well-being of students and staff is our highest priority. We know parents/guardians entrust us with their children and we do not take that responsibility lightly. I know what it means to be a concerned parent and I can assure you that we would not allow our schools to open and operate if there was a risk to students.
Since we updated you last Monday, HDSB Facility Services staff have taken a number of steps to address and investigate the gym roof collapsing and begin planning the rebuild, including:
Assessing the entire site to ensure the safety of the whole school building, including structural inspections in each classroom.
Demolishing the gymnasium to prevent further damage to the school and secure the site.
Meeting with an architect to review the site and develop plans for a new and reinvisioned gym that will serve the Glenview PS community.
Investigating similar schools in the HDSB built by the same contractor to ensure there are no outstanding issues.
Reviewing inspection reports to see if there were any concerns that were missed.
We have developed a Q&A and timeline of events to help answer questions from families. The Q&A is based on questions we have been receiving. We encourage you to view the following documents:
I appreciate your patience and understanding during this time.
Sincerely,
Nick Frankovich
Superintendent of Education
July 3, 2023 - Initial Notice to Glenview PS Families
Dear Glenview PS families,
We are writing to inform you that the gymnasium roof of Glenview PS collapsed over the weekend. As you may be aware, the gymnasium and stage were closed to students and staff prior to the end of the school year due to a safety concern.
As a result of this safety concern, the HDSB had secured a structural engineering company to assess the gym on Thursday, June 29, 2023.
As always, the safety and well-being of students and staff is our highest priority. The school will be closed to all visitors and staff until further notice. The HDSB continues to work with the structural engineers and a restoration company to determine next steps.
We understand there will be many questions regarding the circumstances and timelines for our rebuilding of the gymnasium. We will provide families with a more fulsome update in the weeks ahead.
Wishing all of our Glenview families a great summer.
Sincerely,
Reg Farnand -Principal
Nick Frankovich - Superintendent of Education